Fuel: P’Harcourt Refinery Can’t Take-off As Promised – NNPC 

Published

on

Maduka University

Barely two months after the September completion deadline flop, the Nigerian National Petroleum Commission has explained why it could not deliver the much-awaited Port Harcourt Refinery Company.

In an interview with our correspondent on Monday, the NNPC Chief Corporate Communications Officer, Olufemi Soneye, said the company encountered risks and challenges while carrying out the rehabilitation, being a brownfield project.

He noted that the NNPC began the commissioning of critical equipment and processing units after the mechanical completion in Nigeria.

“You may recall that mechanical completion of the PHRC revamp was successfully achieved several months ago, marking a significant milestone in the project. Following this, we began the commissioning of critical equipment and process units.

Advertisement

“However, as is common with brownfield projects of this scale and complexity, we encountered unforeseen risks and challenges,” he stated.

Nonetheless, he noted that the issues were resolved and commissioning activities have resumed.

Soneye stressed that work is being carried out to ensure the project’s completion.

“These issues have since been effectively resolved, and commissioning activities have resumed.

“Work is being carried out around the clock to ensure the successful completion of this critical project,” he told our correspondent.

Advertisement

Asked if there is any timeline for the completion of the project, he replied, “Shortly.”

It was observed that the NNPC desisted from giving new deadlines for the delivery of the refinery, having failed to meet its deadlines seven times.

The moribund Port Harcourt refinery is one of three owned by the Federal Government and managed by the NNPC.

Nigerians have been hopeful that the cost of fuel could crash if the country refines its crude and ends the import of refined products.

The NNPC said last week that it would continue to import fuel, saying it was not the sole off-taker of petrol at the Dangote refinery.

Advertisement

The refinery, situated in Nigeria’s oil-rich Niger Delta region, has been in operation since 1965, but later became moribund for several years.

In March 2021, the Nigerian government acquired a $1.5bn loan for the renovation and modernisation of the refinery, but the contractor handling the project has yet to announce its completion.

Promises made to Nigerians by the Federal Ministry of Petroleum Resources and the NNPC about the refinery have continued to hit brick walls.

After the failure of the sixth deadline in early August, the then Chief Financial Officer of the NNPC, Umar Ajiya, said the refinery would commence operations in September 2024.

However, September ended without a word from the NNPC about the refinery, and Nigerians have been left in the dark since almost two months ago.

Advertisement

Recall that the contractor overseeing the rehabilitation of the Port Harcourt refinery, Maire Tecnimont SPA, refused to disclose the completion date for the project, despite a formal request from a human rights lawyer, Femi Falana.

Apparently baffled by the delay in the completion of the project, Falana had filed an official request under the Freedom of Information Act, seeking clarity on the date set aside for the project completion.

 In response, Maire Tecnimont’s legal representative, Muyiwa Ogungbenro, a partner at Olajide Oyewole LLP, sent a letter to Falana in early October, declining to reveal the information.

 Ogungbenro stated that the Managing Director of Maire Tecnimont SPA, as part of an independent private contractor, is not obligated to disclose such information under the FOI Act.

 “We are counsel to Maire Tecnimont SpA, and we have our client’s instruction to respond to your letters dated 17 and 24 September 2024 requesting information on the contract between our client and Nigerian National Petroleum Company Ltd.

Advertisement

 “Our client is a private company. Being a private independent contractor, our client is not a company in which any government has a controlling interest, and does not provide public services, functions or utilising public funds for them to be bound by the obligations in the Freedom of Information Act.

 “On this ground, our client regrettably cannot provide the information you have requested,” Ogungbenro declared.

Since then, information about the refinery has been kept from the public, whose hope for cheaper petrol lies in the facility.

From December 2023, NNPC had been giving Nigerians different dates, assuring them that the refinery would begin the sale of refined products soon, having attained mechanical completion.

In July, the Group Chief Executive Officer of the NNPC, Mele Kyari, stated categorically that the refinery would come into operation in early August. He had said in 2019 that the NNPC would deliver all the country’s four refineries before the end of former President Muhammadu Buhari’s administration last year.

Advertisement

When he appeared before the Senate in July, Kyari boasted, “I can confirm to you, Mr Chairman, that by the end of the year, this country will be a net exporter of petroleum products.

“Specific to NNPC refineries, we have spoken to a number of your committees, and it is impossible to have the Kaduna refinery come into operation before December, it will get to December, both Warri and Kaduna; but that of Port Harcourt will commence production early August this year.”

However, the promise was not fulfilled in August which was the sixth postponement.

Though the NNPC said it was on course, the refinery has yet to commence operations even as the fourth quarter of the year nears the end.

The PUNCH recalls that the 210,000 barrels per day refinery was said to have reached what the NNPC called mechanical completion of rehabilitation work in December. It stated that the facility would start refining 60,000 barrels of crude oil daily after last year’s Christmas break.

Advertisement

Later in January, Kyari said the refinery was being tested and would be ready by the end of the first month.

During the second month of the year, the Shell Petroleum Development Company of Nigeria Limited completed the supply of 475,000 barrels of crude oil to the facility, raising the expectations of marketers that production would soon start.

This came a few weeks after the NNPC said in January that it was seeking to engage reputable and credible operations and maintenance companies to run the refinery.

In mid-March, Kyari said the Port Harcourt refinery would commence operations in two weeks, April.

“We are serving this country with honour and dignity. And we will make sure that the promises we make on the rehabilitation of these refineries will take place,” Kyari stated after he appeared before the Senate Ad-hoc Committee investigating the various turnaround maintenance projects of the country’s refineries.

Advertisement

As the April deadline elapsed, independent petroleum marketers told The PUNCH that the facility would begin production by the end of July.

Commenting on this then, NNPC’s spokesman, Soneye, said that regulatory approvals from international bodies were the only impediment stalling the operational commencement of the refinery.

Advertisement
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Business

No Bad Blood Over New Cement Factories, But Our Mining Rights Run Till 2045 — Ibeto Tells Ebonyi Govt

Published

on

Maduka University

ABAKALIKI, EBONYI STATE — Billionaire industrialist and Chairman of Ibeto Group, Dr. Cletus Ibeto, has clarified his position on plans by the Ebonyi State Government to establish a new cement manufacturing plant, saying he has no objection to fresh investment in the state provided his company’s existing mining rights are respected.

Ibeto, who is also a core investor in the Nigerian Cement Company (Nigercem), said the proposed development should not interfere with areas covered by valid mining leases held by his company.

“We are not against the establishment of new cement factories in Ebonyi State. However, such developments must not interfere with or overlap the specific areas where Ibeto Group holds valid Mining Lease Licences issued by the Federal Ministry,” Ibeto stated.

He said the company’s statutory mining leases covering limestone deposits in the Nkalagu axis remain valid until 2045.

Ibeto stressed the need for proper delineation and mapping of mining areas to prevent conflicts between existing title holders and new investors seeking to establish businesses in the state.

Under Nigeria’s legal framework, mineral resources are vested in the Federal Government, with mineral titles administered through the Federal Ministry of Solid Minerals Development and the Mining Cadastre Office.

Nigercem Ready to Resume Operations

Addressing concerns over the future of the historic Nigercem plant, Ibeto said Ibeto Group remains committed to reviving the facility and is ready to commence work once outstanding administrative issues with the state government are resolved.

He said the company’s position should not be interpreted as opposition to new investment in Ebonyi, stressing that his concern was the protection of legally acquired mining rights.

The development could pave the way for both the revival of Nigercem and the entry of new investors into Ebonyi’s cement industry, provided the respective mining areas are clearly mapped out and existing legal titles are respected.

Continue Reading

Business

Patience Jonathan Hails Azikel Boss Eruani as ‘Small Boy’ She Mentored Into Billionaire League

Published

on

Maduka University
Ex-President Goodluck Jonathan’s wife, Patience, has described the Group President of Azikel Group, Dr Azibapu Eruani, as a “small boy” she raised and mentored into the league of Nigeria’s biggest businessmen.

She said her guidance was behind his bold entry into big business at a relatively young age.

The former First Lady spoke on Tuesday in a video which went viral on Thursday during an inspection tour of the Azikel Refinery in Obunagha, Bayelsa State, alongside other dignitaries.

She said she personally introduced Eruani to billionaire businessmen, Aliko Dangote and Aminu Dantata, and pushed him to aspire to their level despite being the youngest among them.

“He’s a boy that I brought up. We are always together. Although he’s the little one among us when we are friends — Dangote, Seyi, Dantata, Eruani — among us, he’s the smallest. But I made sure he followed the Dangotes, he followed Dantata.

“Because I’m a woman in their midst, I made sure I told this small boy, ‘Go and follow them, and stop the grammar.’ But when he told me that one day he would be like Dangote, I said, ‘You’re thinking too high.’ I prayed to God to grant him his heart’s desire,” she said.

The former First Lady also recalled how the immediate past APC administration under Muhammadu Buhari initially failed to grant Eruani a refinery licence before eventually approving three.

“During the Buhari administration, he and others came to me and told me they were going to apply for a refinery. I told him, ‘Eruani, your brother, the President, did not give you a refinery.

“Is it the APC government that will give you one?’ I prayed it would happen. But later, they came back and told me they had been given three refineries,” she said.

The inspection coincided with the arrival of the refinery’s Crude Distillation Unit, a major milestone in the development of the $1bn facility.

The 25,000 barrels-per-day plant is a private hydro-skimming refinery designed to process condensate into petrol, diesel, aviation fuel, kerosene and other products.

It is set to become Nigeria’s second-largest full-slate refinery and the first major privately owned refinery in the Niger Delta.

The Managing Director/Chief Executive Officer of the Niger Delta Development Commission, Samuel Ogbuku, who joined the inspection tour, commended Eruani for his perseverance, noting that he had attended the project’s groundbreaking ceremony eight years ago.

Ogbuku described the refinery as an inspiration and a potential catalyst for investment, job creation and economic growth in Bayelsa State, and urged residents, particularly youths, to key into the opportunities it would create.

He also praised the Bayelsa State Government for improving road infrastructure leading to the refinery site and called for continued support for the project.

Governor Douye Diri, who was represented at the inspection by his deputy, Peter Akpe, has consistently backed the project, which is expected to employ hundreds of workers and drive industrialisation in the state.

Other dignitaries at the event included the Chairman of the Bayelsa State Council of Traditional Rulers, King Bubaraye Dakolo; Vice President of Azikel Group, Presley Asemota; and Isaac Yalah, among others.

Continue Reading

Business

NNPC Announces Increase in Petrol Pump Price

Published

on

Maduka University
The Nigerian National Petroleum Company Limited (NNPCL) has increased the pump price of Premium Motor Spirit, popularly known as petrol, at its retail stations.

A market check on Tuesday showed that NNPCL outlets in Abuja and nearby areas adjusted their petrol price from N1,155 per litre to N1,270 per litre.

The latest adjustment represents an increase of N115 per litre by the state-owned oil company.

Some NNPCL and MRS filling stations in Abuja were reportedly shut, while other outlets reviewed their petrol prices upward on Monday.

The new price change follows recent increases by depot owners and petroleum marketers, who have adjusted their rates twice within a week.

The latest development also comes days after Dangote Refinery resumed the sale of refined petroleum products in dollars, a move that has raised concerns among industry players over the direction of fuel pricing in the country.

Continue Reading

Business

13 Oil Blocks to Return to Licensing Basket After Failing to Attract Bids – NUPRC

Published

on

Maduka University

The Federal Government has disclosed that 13 of the 50 oil and gas blocks offered in the 2025 Licensing Round will be returned to the licensing basket after failing to attract bids from prospective investors.

The Chief Executive of the Nigerian Upstream Petroleum Regulatory Commission (NUPRC), Oritsemeyiwa Eyesan, disclosed this on Tuesday at the 2025 Commercial Bid Conference in Abuja.

Eyesan said that although 50 blocks were initially put up for bidding, prospective investors showed interest in only 37.

“At the end of the exercise, we had 50 blocks on offer, but we only had representation for 37 of those 50 blocks. Thirteen of those blocks will be returning back to the basket,” she said.

She further disclosed that 143 companies participated in the commercial bid process, submitting about 200 bids for the available oil and gas assets.

“We have a total of 143 companies showing interest for 200 bids. That, for us, was remarkable, and I must say thank you,” Eyesan stated.

According to her, nearly 300 companies initially expressed interest in the licensing round, which she described as a sign of renewed investor confidence in Nigeria’s upstream petroleum sector.

“When we started the journey, we got interest from almost 300 companies. I repeat, almost 300 companies. That, in my view, was an indication that the tide has turned for Nigeria,” she said.

She explained that the number of interested companies was reduced to 196 following the prequalification stage, before the process moved to the technical and commercial evaluation phases.

“From the almost 300 interests that we got, we moved to the pre-qualification stage, and that number was pruned down to 196,” she added.

The 2025 Licensing Round was launched on November 11, 2025, in accordance with the Petroleum Industry Act 2021, with 50 oil and gas blocks put up for bidding across seven sedimentary basins.

The assets comprise 16 Niger Delta onshore blocks, 18 shallow-water blocks, one deep offshore block, three blocks in the Benin Basin, four in the Anambra Basin, four in the Chad Basin and four in the Benue Trough.

The bid portal opened on December 1, 2025, while a pre-bid conference was held in Lagos on January 14, 2026, to provide prospective investors with guidance on the bidding requirements.

Registration and prequalification submissions closed on February 27, 2026, with the prequalification process completed on March 16.

The NUPRC said winning bids are being determined through a weighted evaluation that considers signature bonus commitments, proposed work programmes and performance security. The process combines technical and commercial scores rather than relying solely on financial offers.

The framework is aimed at ensuring that Nigeria’s petroleum assets are awarded to investors with the financial capacity, technical expertise and operational strength required to accelerate exploration and production in the country’s upstream sector.

Continue Reading

Business

No More Naira: Dangote Refinery Switches To Dollar For Petrol Sales 

Published

on

Maduka University
Dangote Petroleum Refinery has officially ended naira-denominated sales of refined petroleum products, introducing a dollar-based pricing structure that fixes the ex-depot price of Premium Motor Spirit (PMS), popularly known as petrol, at $0.779 per litre.

The new pricing template, which took effect on July 13, 2026, also pegs Automotive Gas Oil (diesel) at $1.087 per litre and Aviation Turbine Kerosene (ATK) at $0.942 per litre, while coastal deliveries of PMS have been fixed at $1,044.62 per metric tonne.

The development marks the end of naira payments for refined petroleum products, a policy introduced after the commencement of the Federal Government’s naira-for-crude initiative on October 1, 2024.

In a notice issued to petroleum marketers and customers, the refinery announced that all previously issued naira-denominated Proforma Invoices and Deal Recaps for both gantry and coastal transactions had become invalid.

The notice, signed by the refinery’s Group Commercial Operations, directed customers not to make payments against the cancelled invoices, stating that all transactions would now be conducted in United States dollars.

Under the revised pricing schedule, petrol supplied through the gantry will sell for $0.779 per litre, diesel for $1.087 per litre, aviation fuel for $0.942 per litre, while coastal PMS supplies will cost $1,044.62 per metric tonne.

The refinery, however, clarified that the transition does not affect Liquefied Petroleum Gas (LPG), which will continue under its existing payment arrangement.

Industry sources said the decision followed a growing imbalance between the currency used to procure crude oil and that used to sell refined products.

According to the sources, the refinery now receives a larger share of its crude oil from the Nigerian National Petroleum Company Limited (NNPCL) under dollar-denominated supply arrangements, while a significant volume of its refined products had continued to be sold locally in naira.

The resulting mismatch, coupled with exchange-rate volatility and fluctuations in global crude oil prices, reportedly increased the refinery’s foreign exchange exposure and prompted the adoption of a uniform dollar-based pricing framework.

A source familiar with the development explained that the shift became necessary as the volume of naira-denominated crude supplies declined relative to dollar-based crude cargoes.

“The refinery is receiving fewer naira-denominated crude cargoes while a larger proportion of its refined products has continued to be sold in naira. That imbalance, combined with foreign exchange volatility, made the transition to dollar pricing inevitable,” the source said.

The decision is expected to have significant implications for petroleum marketers who source products directly from the refinery for nationwide distribution. It could also influence retail pump prices, depending on movements in the exchange rate, international crude oil prices, logistics costs and marketers’ operating expenses.

The Federal Government had introduced the naira-for-crude policy to encourage domestic refining, reduce pressure on foreign exchange demand and stabilise fuel prices. However, industry stakeholders have recently reported implementation challenges, noting that a growing proportion of crude supplies to local refiners has reverted to dollar-based transactions.

Analysts believe the latest development underscores the continued foreign exchange challenges facing Nigeria’s downstream petroleum sector despite efforts to deepen local refining and reduce dependence on imported fuel.

Continue Reading
Advertisement

Trending